Assignment -10 | Project Timeline Management: Tracking Tasks and Visualizing Progress in Excel

Excepted timing : 5 minutes

| Task            | Start Date | End Date   | Status      |
|-----------------|------------|------------|-------------|
| Task A          | 2023-01-01 | 2023-01-10 | Complete    |
| Task B          | 2023-01-05 | 2023-01-15 | In Progress |
| Task C          | 2023-01-08 | 2023-01-18 | Not Started |
| Task D          | 2023-01-02 | 2023-01-12 | In Progress |
| Task E          | 2023-01-06 | 2023-01-16 | Not Started |
| Task F          | 2023-01-10 | 2023-01-20 | Not Started |
| Task G          | 2023-01-12 | 2023-01-22 | Not Started |
| Task H          | 2023-01-15 | 2023-01-25 | Not Started |
| Task I          | 2023-01-18 | 2023-01-28 | Not Started |
| Task J          | 2023-01-22 | 2023-01-31 | Not Started |
| Task K          | 2023-01-25 | 2023-02-05 | Not Started |
| Task L          | 2023-01-28 | 2023-02-08 | Not Started |
| Task M          | 2023-01-30 | 2023-02-10 | Not Started |

 
Task :
  1. Calculate the duration of each task using DATEDIF function.
  2. Calculate the total project duration using formulas.
  3. Use data validation to create a drop-down list for selecting task statuses (Complete, In Progress, Not Started).
  4. Apply conditional formatting to highlight tasks that are overdue (End Date < Today).
  5. Create a Gantt chart to visualize the project timeline with tasks and their durations.

To perform the tasks outlined in Assignment  using Excel, follow these step-by-step instructions:

 

Step to Perform

1.      Calculate Duration of Each Task Using DATEDIF Function:

2.      Calculate Total Project Duration:

3.      Use Data Validation for Task Statuses:

4.      Apply Conditional Formatting for Overdue Tasks:

5.      Create a Gantt Chart to Visualize Project Timeline: